Quick Answer
What should you do if your bulk activewear order arrives with defects?
Set aside the affected stock and keep the carton labels with it. Check the defect against the approved specification, record how many units you inspected and how many failed, and send the manufacturer a written notice while the checks continue. Agree which stock can be released, what needs further inspection, and whether sorting, rework or replacement makes sense.
Picture a launch a week away. Your warehouse finds black size-M leggings with visibly different inseams. The inventory system lists them under one SKU. The carton labels are what let you work out whether you can still ship part of the order on time. Before anyone moves the stock, record which carton each pair came from and keep the opened cartons separate.
What to Record Before You Contact the Factory
A clear first message lets the factory find its records and repeat your check. For a short-inseam complaint, take one photo showing the full measurement path, then take a close-up of the reading. Keep a few marked garments in their original condition. If you wash, wear-test or repair a piece to investigate the issue, identify that piece separately in your records.
- Order and stock. Include the PO, style, color, size, carton ID and any lot number visible on the labels.
- Agreed requirement. Attach the relevant page of the approved tech pack, size chart, artwork or test requirement.
- Findings. Give the number inspected and the number affected for each carton or lot. If one garment has two defects, record one affected garment and two defect observations.
- What you need next. Ask the factory to confirm receipt, identify any related stock and give a date for reviewing the evidence with you.
Example First Email for a Garment Quality Claim
Subject — PO 1234 | Black size-M leggings | Short inseams in carton A01
We checked 25 pairs from carton A01 and found five below the agreed 69.0 cm minimum inseam. We’ve put A01 on hold and are checking the other cartons. The approved measurement page, photos and readings are attached.
Could you check which cutting bundle or sewing run was packed into A01 and tell us whether other cartons contain units from the same run? Please confirm receipt and let us know when you can review the measurements with us.
Check the agreement for the required notice channel and deadline. Where the CISG applies, Articles 38 and 39 of the convention address examination and notice of nonconformity. Send the findings you can confirm now and update the factory when the rest of the stock has been checked.
Which Specification Should You Use to Verify the Defect?
Pull the approved tech pack revision, size chart, tolerances and pre-production sample used for the bulk order. If a measurement on the sample differs from the written chart, check which reference the order documents specify and look for any signed revision. A late change to the inseam can leave the brand and factory working from different files.
When two inspectors disagree, give them the same marked garment and ask each to measure it using the approved method. Keep both readings. For leggings with a gusset, one person might start the tape at the crotch seam junction while another starts at the edge of the gusset. Settle the start point and tape path before spending time measuring another carton. The activewear tech pack checklist shows how to record measurement points and changes.
What to check when different activewear defects show up
| What the buyer found |
Reference to pull |
What to check next |
| Leggings with uneven or short inseams |
Approved measurement points and size tolerance |
Measure the same marked pair again. Check both legs if the complaint is uneven length. |
| Sports bra seam opening during wear |
Approved seam construction and any agreed performance test |
Record exactly where the seam opened and under what conditions. Use the agreed procedure to check retained pieces. |
| Logo peeling after a wash |
Approved logo application, care instructions and any agreed wash procedure |
Record how the failed item was washed and dried. Keep an unwashed piece from the same lot for comparison and any agreed retest. |
| A bra and matching legging look different in color |
Approved color reference and any agreed shade range |
Compare the pieces under the agreed lighting. Record their fabric lots and which pieces were intended to be sold together. |
| Incorrect barcodes on identical-looking bags |
Approved barcode file and SKU packing list |
Open selected bags and verify the actual garment, size label and barcode as one unit before approving any relabeling. |
What Four Cartons Tell You About a Short-Inseam Problem
This is a simulated inspection. The carton IDs, quantities, measurements and email above are illustrative. In the example, the approved inseam is 70.0 cm ± 1.0 cm, measured flat and relaxed from the crotch seam junction to the hem. The acceptable range is 69.0–71.0 cm. A pair measuring 68.5 cm falls 0.5 cm below the lower limit.
Simulated receiving check for black size-M leggings
| Carton |
Pairs checked |
Outside tolerance |
Share outside tolerance |
| A01 | 25 | 5 | 20% |
| A02 | 25 | 2 | 8% |
| B01 | 25 | 1 | 4% |
| B02 | 25 | 0 | 0% |
| Total checked | 100 | 8 | 8% |
A01 and A02 account for seven of the eight pairs outside tolerance. Start tracing there, then pull the one short pair from B01. It could connect the problem to another carton packed from the same production run. If the factory’s records show that the run went into more cartons, put those cartons on hold too. If the records are incomplete, agree which stock needs sorting before anything in that group is released.
The 8% describes the 100 pairs checked. The zero in B02 describes the 25 pairs inspected in that carton. A formal lot acceptance decision follows the sampling plan and criteria agreed for the order. ISO 2859-1 describes acceptance sampling schemes indexed by AQL.
Once the two teams agree on the measurement, compare short pairs with in-tolerance pairs from the same size. Check the finished hem depth and ask the factory to compare the corresponding cutting and sewing records. A short finished inseam can send you looking in several places. The comparison gives the factory a starting point. See the bulk activewear quality control checkpoints for the production steps where those records can help.
Decide Which Stock You Can Release Before the Claim Is Resolved
Ask the warehouse for the quantity it can identify and verify by SKU and carton. The total number of leggings in the building matters less to the launch team than how many verified pairs it has in each size. Releasing a partial quantity may keep some orders moving, provided the checked stock stays separate and the release follows the agreed criteria.
For each group, record three figures in the same update to the warehouse and manufacturer: how many units have been checked and cleared, how many remain on hold, and how many still need checking. Give the held stock a visible location or status so it stays out of pick-and-pack. Concerns involving product safety or mandatory labeling need to stay on hold while the applicable requirements are verified.
When Rework Makes Sense and When to Ask for Replacements
For the pair measuring 68.5 cm, the factory needs to recover at least 0.5 cm to reach the lower limit. Ask how much usable fabric is inside the hem and whether it can be resewn to the approved finish. Have the factory repair one pair first. Remeasure both legs, compare the new hem with the sample, and look for old needle marks or puckering. A technically longer leg still has to look right on the finished garment.
How to choose a remedy and what to agree in writing
| Option |
When it makes sense |
What to agree |
| Sort and release verified stock |
The warehouse or factory can identify affected units with a reliable check. |
Which cartons to inspect, the check to use, who pays for sorting and how verified units will be marked. |
| Rework |
A trial restores the approved measurement, appearance or function. |
Approved trial, units covered, repair location, completion date and criteria for passing reinspection. |
| Replacement |
The repair fails or the corrected pieces will miss the date the buyer needs them. |
Quantities by size and color, shade match where relevant, inspection before dispatch and delivery date. |
| Price adjustment |
The goods remain suitable for an agreed use and both parties can settle on terms. |
Affected quantities, basis for the adjustment and how the goods may be used or sold. |
Compare dates the warehouse can act on. If one proposal gives a rework completion date and the other gives a replacement dispatch date, ask for the expected date each option will be checked, delivered and ready to release. For a small barcode mix-up, local sorting and relabeling may be practical. For a sports bra seam that opens during the agreed test, first verify whether a trial repair restores the performance you approved. Financial remedies depend on the purchase agreement, the facts and applicable law.
What to Check Before You Close the Claim
Run the original check again and inspect anything the repair could have changed. On the leggings, record the new inseam on both legs and check the hem finish. On a relabeled item, scan the new barcode and verify it against the garment inside the bag. On replacements for a coordinated set, compare the shade with stock you already hold if both will be sold together.
Ask for the reinspection results by SKU and carton. The record should show which quantities passed, where those cartons are, and what still needs action. If only part of the order has been corrected, record the outstanding quantity and the next delivery date while the claim is still open.
Write the Missing Check Into Your Next Bulk Order
Use the part that slowed you down. If the buyer and factory measured from different points, put a marked photo beside the measurement row. If nobody could tell which other cartons contained units from the same run, agree how those carton IDs will be linked to production records. If a reworked hem met the length but left visible marks, add the appearance requirement to the approval criteria.
For your next custom yoga pants and leggings order, decide which measurements and finishes need that level of detail before sample approval. The Call The STYLE activewear quality control service explains where checks can fit into sampling, production and final inspection.
Plan the Quality Checks for Your Next Activewear Order
Send your tech pack or approved sample details and tell us which issue you want to prevent in the next run. Call The STYLE can discuss where to check it during sampling, bulk production and final inspection.
Discuss Your Activewear QC Requirements
Frequently Asked Questions
Can I report defects after the shipment passes a pre-shipment inspection?
Yes. Report the specific defect and record the approved requirement, affected stock and evidence. Include the pre-shipment report so both teams can see what was checked. The agreement, applicable law and facts determine the remedies available.
Does AQL 2.5 mean I can reject a shipment when more than 2.5% of the pieces I checked fail?
Use the acceptance and rejection numbers from the agreed sampling plan. AQL 2.5 is an index used in selecting the plan. A targeted check of suspect cartons can help trace the problem, and its results should be recorded separately from a formal acceptance inspection.
What if I find the problem only after washing or wearing the garment?
Record the item, lot, conditions and result. Keep an unused piece from the same lot if one is available. Check the approved care instructions and any agreed test method, and send the factory your findings while arranging a repeat check.
What if we found a defect but still need part of the order for launch?
Work by SKU and carton. Identify and verify the stock that meets the agreed release criteria, record the quantities you can use, and keep suspect units on hold. Give the launch team the verified size breakdown so it can decide which orders it can fill.